DescriptionSituation
Overall status of expressway constructionAbout 98 percent complete
main carriageway work99 percent complete
Section between Meerut and Budaun130 km construction ready for trial
Proposed trial run time1st week of December 2025
Expressway inaugurated2nd week of January 2026
Travel time from Meerut to Prayagraj (after expressway)Only 6 hours